Echols Grove Solar (25INR0368)

Echols Grove Solar is a 201.6 MW solar interconnection project in Lamar, Texas with a current status of operational. It is proposed to connect at Tap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770).

201.6 MWCapacity
OperationalStatus
LamarMarket
SolarTechnology

Project facts

Canonical nameEchols Grove Solar
Queue ID25INR0368
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketLamar
TechnologySolar
Capacity201.6 MW
StateTexas
CountyLamar
Point of interconnectionTap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770)
Requested (queue) date2023-04-07
Proposed in-service date
Operational date2027-04-03
Withdrawn date
DeveloperEchols Grove, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata