ECKERTY - BUECHLER 69.0kV (J3767)

ECKERTY - BUECHLER 69.0kV is a 38.0 MW solar interconnection project in Crawford, Indiana with a current status of withdrawn. It is proposed to connect at ECKERTY - BUECHLER 69.0kV.

38.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameECKERTY - BUECHLER 69.0kV
Queue IDJ3767
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity38.0 MW
StateIndiana
CountyCrawford
Point of interconnectionECKERTY - BUECHLER 69.0kV
Requested (queue) date2024-04-18
Proposed in-service date2028-09-30
Operational date2028-09-30
Withdrawn date2025-09-23
Developer—
Utility / transmission ownerHoosier Energy

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-24phaseStudy Not StartedPhase 2low
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.