Edgeley 115 kV Substation (GEN-2024-SR12)
Edgeley 115 kV Substation is a 20.0 MW battery interconnection project in La Moure County, North Dakota with a current status of withdrawn. It is proposed to connect at Edgeley 115 kV Substation.
20.0 MWCapacity
WithdrawnStatus
NDMarket
BatteryTechnology
Project facts
| Canonical name | Edgeley 115 kV Substation |
|---|---|
| Queue ID | GEN-2024-SR12 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | ND |
| Technology | Battery |
| Capacity | 20.0 MW |
| State | North Dakota |
| County | La Moure County |
| Point of interconnection | Edgeley 115 kV Substation |
| Requested (queue) date | 2024-05-21 |
| Proposed in-service date | 2026-10-01 |
| Operational date | — |
| Withdrawn date | 2026-06-09 |
| Developer | — |
| Utility / transmission owner | WAPA/BEPC/HCPD Integrated System |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata