WAPA/BEPC/HCPD Integrated System — Interconnection Queue Projects
WAPA/BEPC/HCPD Integrated System is associated with 386 tracked interconnection projects representing 63,982 MW of requested capacity.
Entity resolution: this utility / transmission entity rolls up 6 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
386Projects
37Active
76Operational
272Withdrawn
63,982 MWRequested capacity
2Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 247 | 39,783 MW |
| Coal | 22 | 8,419 MW |
| Solar | 39 | 7,039 MW |
| Gas | 41 | 4,546 MW |
| Battery | 9 | 2,120 MW |
| Solar+Battery | 3 | 1,916 MW |
| Other | 11 | 78 MW |
| Diesel | 10 | 60 MW |
| Hydro | 3 | 18 MW |
| Oil | 1 | 2 MW |
Portfolio by market
Geographic footprint
| State | Projects |
|---|---|
| South Dakota | 163 |
| North Dakota | 113 |
| Montana | 45 |
| Iowa | 23 |
| Nebraska | 15 |
| Minnesota | 11 |
| Wyoming | 6 |
| Arizona | 5 |
| Colorado | 3 |
| California | 1 |
| New Mexico | 1 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| West Queue Project GI-0612 — Wind in Hand, South Dakota | GI-0612 | Wind | 2,000.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0609 — Wind in Buffalo, South Dakota | GI-0609 | Wind | 1,500.0 MW | withdrawn | Buffalo, South Dakota |
| West Queue Project GI-0611 — Wind in Hand, South Dakota | GI-0611 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| Broadview | 2308 | Solar+Battery | 816.4 MW | active | Fresno, California |
| West Queue Project GI-1407 — Gas in Emmons, North Dakota | GI-1407 | Gas | 800.0 MW | withdrawn | Emmons, North Dakota |
| West Queue Project GI-1408 — Gas in Emmons, North Dakota | GI-1408 | Gas | 800.0 MW | withdrawn | Emmons, North Dakota |
| West Queue Project GI-0111a — Coal in Mcpherson, South Dakota | GI-0111a | Coal | 750.0 MW | withdrawn | Mcpherson, South Dakota |
| West Queue Project GI-0111 — Coal in Mcintosh, North Dakota | GI-0111 | Coal | 750.0 MW | withdrawn | Mcintosh, North Dakota |
| West Queue Project GI-0610 — Coal in Stanley, South Dakota | GI-0610 | Coal | 700.0 MW | withdrawn | Stanley, South Dakota |
| West Queue Project GI-0702 — Coal in Campbell, South Dakota | GI-0702 | Coal | 700.0 MW | withdrawn | Campbell, South Dakota |
| West Queue Project GI-0517 — Coal in Campbell, South Dakota | GI-0517 | Coal | 700.0 MW | withdrawn | Campbell, South Dakota |
| West Queue Project GI-0804 — Wind in Logan, North Dakota | GI-0804 | Wind | 672.0 MW | withdrawn | Logan, North Dakota |
| West Queue Project GI-0408 — Coal in Clay, South Dakota | GI-0408 | Coal | 600.0 MW | withdrawn | Clay, South Dakota |
| West Queue Project GI-1405 — Wind in Banner, Nebraska | GI-1405 | Wind | 600.0 MW | withdrawn | Banner, Nebraska |
| West Queue Project 2023-MP2 — Solar+Battery in Mohave, Arizona | 2023-MP2 | Solar+Battery | 600.0 MW | active | Mohave, Arizona |
| West Queue Project GI-0321 — Coal in Mercer, North Dakota | GI-0321 | Coal | 510.0 MW | withdrawn | Mercer, North Dakota |
| Flagstaff - Glen Canyon 345 | 2023-G5.2 | Solar | 500.0 MW | withdrawn | Coconino County, Arizona |
| West Queue Project GI-0318 — Coal in Beadle, South Dakota | GI-0318 | Coal | 500.0 MW | withdrawn | Beadle, South Dakota |
| West Queue Project 2024-MP1 — Battery in Mohave, Arizona | 2024-MP1 | Battery | 500.0 MW | active | Mohave, Arizona |
| West Queue Project GI-0325 — Coal in Custer, Montana | GI-0325 | Coal | 500.0 MW | withdrawn | Custer, Montana |
| West Queue Project GI-0217 — Coal in Stark, North Dakota | GI-0217 | Coal | 500.0 MW | withdrawn | Stark, North Dakota |
| West Queue Project GI-1106 — Coal in Pennington, South Dakota | GI-1106 | Coal | 500.0 MW | withdrawn | Pennington, South Dakota |
| West Queue Project 2024-MP2 — Battery in Mohave, Arizona | 2024-MP2 | Battery | 500.0 MW | active | Mohave, Arizona |
| West Queue Project 2023-MP1 — Solar+Battery in Yavapai, Arizona | 2023-MP1 | Solar+Battery | 500.0 MW | active | Yavapai, Arizona |
| West Queue Project GI-0319 — Coal in Clay, South Dakota | GI-0319 | Coal | 500.0 MW | withdrawn | Clay, South Dakota |
| Jamestown 230 kV Substation | GEN-2023-114 | Wind | 425.0 MW | withdrawn | LaMoure & Stutsman, North Dakota |
| West Queue Project GI-0824 — Wind in Buffalo, South Dakota | GI-0824 | Wind | 400.0 MW | withdrawn | Buffalo, South Dakota |
| Miles City 2 - Rosebud Creek 230kV Line | GEN-2022-097 | Wind | 400.0 MW | withdrawn | Rosebud And Cluster, Montana |
| West Queue Project GI-0911 — Wind in Morton, North Dakota | GI-0911 | Wind | 400.0 MW | withdrawn | Morton, North Dakota |
| West Queue Project GI-0206 — Coal in Adams, North Dakota | GI-0206 | Coal | 400.0 MW | withdrawn | Adams, North Dakota |
| Archer - Stegall 230kV | 2023-G1 | Solar | 400.0 MW | active | Scotts Bluff County, Nebraska |
| West Queue Project GI-1404 — Wind in Billings, North Dakota | GI-1404 | Wind | 383.0 MW | active | Billings, North Dakota |
| Fort Thompson 345 kV Substation | GEN-2022-174 | Solar | 370.0 MW | withdrawn | Buffalo And Hyde, South Dakota |
| Shiprock 345- Sub | 2018-G6 | Solar | 360.0 MW | active | San Juan County, New Mexico |
| Belfield 230 kV Substation | GEN-2022-219 | Solar | 350.0 MW | withdrawn | Dawson, Montana |
| Dawson Co - Ft Peck 230 kV | GEN-2017-109 | Wind | 320.9 MW | withdrawn | Dawson County, Montana |
| Morris - Moorhead 230kV Line | GEN-2024-269 | Solar | 315.0 MW | withdrawn | OtterTail, Minnesota |
| West Queue Project GI-0114 — Wind in Mcintosh, North Dakota | GI-0114 | Wind | 300.0 MW | withdrawn | Mcintosh, North Dakota |
| South Huntley 230 kV Substation | ASGI-2024-012 | Solar | 300.0 MW | operational | Big Horn, Montana |
| West Queue Project GI-0118 — Wind in Codington, South Dakota | GI-0118 | Wind | 300.0 MW | withdrawn | Codington, South Dakota |
| West Queue Project GI-0115 — Wind in Mcintosh, North Dakota | GI-0115 | Wind | 300.0 MW | withdrawn | Mcintosh, North Dakota |
| West Queue Project GI-0810 — Wind in Meade, South Dakota | GI-0810 | Wind | 300.0 MW | withdrawn | Meade, South Dakota |
| West Queue Project GI-0112 — Wind in Dickey, North Dakota | GI-0112 | Wind | 300.0 MW | withdrawn | Dickey, North Dakota |
| Philip Tap 230 kV | GEN-2017-014 | Wind | 300.0 MW | active | Haakon County, South Dakota |
| West Queue Project GI-0707a — Wind in Logan, North Dakota | GI-0707a | Wind | 286.0 MW | withdrawn | Logan, North Dakota |
| Vfodnes-Utica Jct. 230kV | GEN-2017-175 | Wind | 270.0 MW | active | Turner, South Dakota |
| Bismarck - Jamestown 230 kV | GEN-2023-144 | Solar | 265.0 MW | withdrawn | Stutsman, North Dakota |
| Tap Bismark – Mound Ridge 230 kV | GEN-2016-035 | Wind | 264.5 MW | withdrawn | Burleigh County, North Dakota |
| Custer - Dawson City 230 kV Line | GEN-2024-224 | Wind | 261.0 MW | withdrawn | Rosebud, Montana |
| Craig - Ault 345- | 2019-G1 | Wind | 252.0 MW | active | Albany County, Wyoming |
| Craig - Ault 345- | 2019-G2 | Wind | 252.0 MW | active | Albany County, Wyoming |
| West Queue Project GI-1503 — Wind in Williams, North Dakota | GI-1503 | Wind | 250.7 MW | active | Williams, North Dakota |
| Maurine 230 kV sub | GEN-2017-020 | Wind | 250.0 MW | withdrawn | Perkins County, South Dakota |
| West Queue Project GI-1006 — Wind in Williams, North Dakota | GI-1006 | Wind | 250.0 MW | withdrawn | Williams, North Dakota |
| West Queue Project GI-1211 — Wind in Williams, North Dakota | GI-1211 | Wind | 250.0 MW | withdrawn | Williams, North Dakota |
| West Queue Project GI-0002 — Wind in Buffalo, South Dakota | GI-0002 | Wind | 250.0 MW | withdrawn | Buffalo, South Dakota |
| West Queue Project GI-0103 — Wind in Codington, South Dakota | GI-0103 | Wind | 250.0 MW | withdrawn | Codington, South Dakota |
| West Queue Project GI-1305 — Wind in Williams, North Dakota | GI-1305 | Wind | 250.0 MW | withdrawn | Williams, North Dakota |
| Hebron 230 kV Substation | GEN-2023-198 | Solar | 250.0 MW | withdrawn | Stark, North Dakota |
| West Queue Project GI-0406 — Wind in Valley, Montana | GI-0406 | Wind | 250.0 MW | withdrawn | Valley, Montana |
| West Queue Project GI-0709 — Wind in Pondera, Montana | GI-0709 | Wind | 250.0 MW | withdrawn | Pondera, Montana |
| West Queue Project GI-0806 — Wind in Stutsman, North Dakota | GI-0806 | Wind | 250.0 MW | withdrawn | Stutsman, North Dakota |
| Philip 230kV Substation | GEN-2017-223 | Wind | 250.0 MW | withdrawn | Haakon County, South Dakota |
| Ault 345 station | 2025-G1 | Solar | 250.0 MW | active | Weld County,, Colorado |
| West Queue Project GI-1306 — Wind in Bon Homme, South Dakota | GI-1306 | Wind | 250.0 MW | withdrawn | Bon Homme, South Dakota |
| West Queue Project GI-0705 — Wind in Yankton, South Dakota | GI-0705 | Wind | 250.0 MW | withdrawn | Yankton, South Dakota |
| West Queue Project GI-0822 — Wind in Pondera, Montana | GI-0822 | Wind | 250.0 MW | withdrawn | Pondera, Montana |
| 7.5 Miles City to Dawson 230 kV Line | GEN-2022-220 | Solar | 250.0 MW | withdrawn | Stark, North Dakota |
| West Queue Project GI-1216 — Wind in Bon Homme, South Dakota | GI-1216 | Wind | 250.0 MW | withdrawn | Bon Homme, South Dakota |
| Philip Tap 230 kV | GEN-2017-019 | Wind | 250.0 MW | withdrawn | Haakon County, South Dakota |
| West Queue Project GI-0909 — Wind in Stutsman, North Dakota | GI-0909 | Wind | 250.0 MW | withdrawn | Stutsman, North Dakota |
| West Queue Project GI-0707 — Wind in Mchenry, North Dakota | GI-0707 | Wind | 241.5 MW | withdrawn | Mchenry, North Dakota |
| Dawson County-Miles City 2 230 kV line | GEN-2024-223 | Wind | 241.0 MW | withdrawn | Dawson, Montana |
| Chappelle Creek 345kV | GEN-2016-103 | Wind | 240.0 MW | withdrawn | Hyde, South Dakota |
| West Queue Project GI-0604 — Wind in Crawford, Iowa | GI-0604 | Wind | 240.0 MW | withdrawn | Crawford, Iowa |
| West Queue Project GI-0704 — Gas in Brookings, South Dakota | GI-0704 | Gas | 240.0 MW | operational | Brookings, South Dakota |
| West Queue Project GI-0718 — Wind in Holt, Nebraska | GI-0718 | Wind | 234.0 MW | operational | Holt, Nebraska |
| Belfield 230 kV Substation | GEN-2024-326 | Battery | 225.0 MW | withdrawn | Stark, North Dakota |
| Miles City 230 kV Substation | GEN-2024-216 | Wind | 225.0 MW | withdrawn | Custer, Montana |
| West Queue Project GI-0514 — Wind in Lyman, South Dakota | GI-0514 | Wind | 225.0 MW | withdrawn | Lyman, South Dakota |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-22 | Campbell County 230 kV line | proposed_online_date | 2026-12-31 | 2028-12-31 |
| 2026-08-22 | Campbell County 230 kV line | capacity_mw | 98.9 | 98.6 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.