EE CT DER Group Study (1536)
EE CT DER Group Study is a 3.7 MW solar interconnection project in Litchfield, Connecticut with a current status of withdrawn. It is proposed to connect at EE WINSTED 33B/CAMPVILLE.
3.7 MWCapacity
WithdrawnStatus
CTMarket
SolarTechnology
Project facts
| Canonical name | EE CT DER Group Study |
|---|---|
| Queue ID | 1536 |
| Status | withdrawn |
| Source status | W |
| Market | CT |
| Technology | Solar |
| Capacity | 3.7 MW |
| State | Connecticut |
| County | Litchfield |
| Point of interconnection | EE WINSTED 33B/CAMPVILLE |
| Requested (queue) date | 2024-05-15 |
| Proposed in-service date | 2024-07-01 |
| Operational date | — |
| Withdrawn date | 2024-05-29 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata