EL CENTRO 1 (286)

EL CENTRO 1 is a 375.0 MW gas interconnection project in Imperial, California with a current status of withdrawn. It is proposed to connect at Southwest Power Link 500kV line.

375.0 MWCapacity
WithdrawnStatus
—Market
GasTechnology

Project facts

Canonical nameEL CENTRO 1
Queue ID286
Statuswithdrawn
Source statusWITHDRAWN
Market—
TechnologyGas
Capacity375.0 MW
StateCalifornia
CountyImperial
Point of interconnectionSouthwest Power Link 500kV line
Requested (queue) date2007-12-20
Proposed in-service date—
Operational date—
Withdrawn date2008-05-07
Developer—
Utility / transmission ownerSDGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata