El Centro Hybrid (389_2A)

El Centro Hybrid is a 89.9 MW gas interconnection project in Imperial, California with a current status of operational.

89.9 MWCapacity
OperationalStatus
IIDMarket
GasTechnology

Project facts

Canonical nameEl Centro Hybrid
Queue ID389_2A
Statusoperational
Source status(OP) Operating
MarketIID
TechnologyGas
Capacity89.9 MW
StateCalifornia
CountyImperial
Point of interconnection
Requested (queue) date
Proposed in-service date
Operational date1993-06-01
Withdrawn date
Developer
Utility / transmission ownerImperial Irrigation District

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectoperationalhigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata