Eldred-Frackville 230kV (AD1-065)

Eldred-Frackville 230kV is a 175.8 MW wind interconnection project in Schuylkill, Pennsylvania with a current status of withdrawn.

175.8 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameEldred-Frackville 230kV
Queue IDAD1-065
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity175.8 MW
StatePennsylvania
CountySchuylkill
Point of interconnection
Requested (queue) date2017-08-31
Proposed in-service date2020-12-31
Operational date
Withdrawn date2018-10-15
Developer
Utility / transmission ownerPPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.