Erick 138kV Substation (GEN-2020-SR1)

Erick 138kV Substation is a 40.0 MW battery interconnection project in Beckham, Oklahoma with a current status of withdrawn. It is proposed to connect at Erick 138kV Substation.

40.0 MWCapacity
WithdrawnStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameErick 138kV Substation
Queue IDGEN-2020-SR1
Statuswithdrawn
Source statusTERMINATED
MarketOK
TechnologyBattery
Capacity40.0 MW
StateOklahoma
CountyBeckham
Point of interconnectionErick 138kV Substation
Requested (queue) date2020-08-04
Proposed in-service date2024-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerWFEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata