Exell Substation 115 kV Sub (GEN-2009-024S)

Exell Substation 115 kV Sub is a 18.0 MW wind interconnection project in Masterson, Texas with a current status of withdrawn. It is proposed to connect at Exell Substation 115 kV Sub.

18.0 MWCapacity
WithdrawnStatus
TXMarket
WindTechnology

Project facts

Canonical nameExell Substation 115 kV Sub
Queue IDGEN-2009-024S
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyWind
Capacity18.0 MW
StateTexas
CountyMasterson
Point of interconnectionExell Substation 115 kV Sub
Requested (queue) date2009-06-15
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata