Eytcheson Ranches Solar (24INR0120)

Eytcheson Ranches Solar is a 76.4 MW solar interconnection project in Navarro, Texas with a current status of operational. It is proposed to connect at Tap 69kV 186 Navarro Mills – 107 Prairie Hill.

76.4 MWCapacity
OperationalStatus
NavarroMarket
SolarTechnology

Project facts

Canonical nameEytcheson Ranches Solar
Queue ID24INR0120
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketNavarro
TechnologySolar
Capacity76.4 MW
StateTexas
CountyNavarro
Point of interconnectionTap 69kV 186 Navarro Mills – 107 Prairie Hill
Requested (queue) date2021-09-14
Proposed in-service date
Operational date2028-01-01
Withdrawn date
DeveloperGransolar Texas Four LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.