Farrier Station Energy Storage (24INR0374)

Farrier Station Energy Storage is a 409.9 MW battery interconnection project with a current status of withdrawn. It is proposed to connect at MONTICELLO SES (BUS# 1696) - ALLEN SWITCH (BUS# 2514).

409.9 MWCapacity
WithdrawnStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameFarrier Station Energy Storage
Queue ID24INR0374
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologyBattery
Capacity409.9 MW
State
County
Point of interconnectionMONTICELLO SES (BUS# 1696) - ALLEN SWITCH (BUS# 2514)
Requested (queue) date2023-01-17
Proposed in-service date2028-06-01
Operational date
Withdrawn date
DeveloperFarrier Station Energy Storage Project, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-28

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.