Fayetteville - Marigold 138 kV Line Tap (J1035)

Fayetteville - Marigold 138 kV Line Tap is a 75.0 MW solar interconnection project in Washington County, Illinois with a current status of withdrawn. It is proposed to connect at Fayetteville - Marigold 138 kV Line Tap.

75.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameFayetteville - Marigold 138 kV Line Tap
Queue IDJ1035
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity75.0 MW
StateIllinois
CountyWashington County
Point of interconnectionFayetteville - Marigold 138 kV Line Tap
Requested (queue) date2018-03-12
Proposed in-service date2021-07-01
Operational date2021-07-01
Withdrawn date2018-10-15
Developer
Utility / transmission ownerAMEREN ILLINOIS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata