Feather Dalea BESS is a 200.0 MW other interconnection project in Glasscock, Texas with a current status of operational. It is proposed to connect at 59902 Sand_Bluff 345kV .

200.0 MWCapacity
OperationalStatus
GlasscockMarket
OtherTechnology

Project facts

Canonical nameFeather Dalea BESS
Queue ID27INR0371
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketGlasscock
TechnologyOther
Capacity200.0 MW
StateTexas
CountyGlasscock
Point of interconnection59902 Sand_Bluff 345kV
Requested (queue) date2024-10-01
Proposed in-service date—
Operational date2027-07-02
Withdrawn date—
DeveloperRWE Solar Development, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.