Fenton - Chanarambie 115kV Line (J874)

Fenton - Chanarambie 115kV Line is a 150.0 MW solar interconnection project in Murray County, Minnesota with a current status of operational. It is proposed to connect at Fenton - Chanarambie 115kV Line.

150.0 MWCapacity
OperationalStatus
Market
SolarTechnology

Project facts

Canonical nameFenton - Chanarambie 115kV Line
Queue IDJ874
Statusoperational
Source statusDone
Market
TechnologySolar
Capacity150.0 MW
StateMinnesota
CountyMurray County
Point of interconnectionFenton - Chanarambie 115kV Line
Requested (queue) date2017-06-16
Proposed in-service date2021-09-30
Operational date2021-09-30
Withdrawn date
Developer
Utility / transmission ownerNORTHERN STATES POWER COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.