Fierce River BESS (27INR0222)

Fierce River BESS is a 284.5 MW other interconnection project in Starr, Texas with a current status of operational. It is proposed to connect at Tapping the 345 kV Line from Del Sol (Bus# 80355) to Frontera (Bus# 80119) ckt 1.

284.5 MWCapacity
OperationalStatus
StarrMarket
OtherTechnology

Project facts

Canonical nameFierce River BESS
Queue ID27INR0222
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketStarr
TechnologyOther
Capacity284.5 MW
StateTexas
CountyStarr
Point of interconnectionTapping the 345 kV Line from Del Sol (Bus# 80355) to Frontera (Bus# 80119) ckt 1
Requested (queue) date2024-03-22
Proposed in-service date
Operational date2029-02-22
Withdrawn date
DeveloperRio Grande River Solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata