FL Queue Project 027076 — Solar in Sumter, Florida

FL Queue Project 027076 — Solar in Sumter, Florida is a 560.0 MW solar interconnection project in Sumter, Florida with a current status of withdrawn. It is proposed to connect at Sumter Substation.

560.0 MWCapacity
WithdrawnStatus
FLMarket
SolarTechnology

Project facts

Canonical nameFL Queue Project 027076 — Solar in Sumter, Florida
Queue ID027076
Statuswithdrawn
Source statusWithdrawn
MarketFL
TechnologySolar
Capacity560.0 MW
StateFlorida
CountySumter
Point of interconnectionSumter Substation
Requested (queue) date2016-05-06
Proposed in-service date2021-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerDuke Energy Progress

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: duke-def-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata