interXdata tracks 2,080 interconnection projects in Florida representing 280,925 MW of requested capacity. The dominant technology by capacity is Gas. The most active counties are Polk, Hillsborough, Osceola.

2,080Total projects
356Active
979Operational
710Withdrawn
280,925 MWRequested capacity
40,173 MWActive capacity

Technology mix

TechnologyProjectsRequested capacity
Gas601156,194 MW
Solar1,15679,547 MW
Other21128,667 MW
Battery738,157 MW
Nuclear74,780 MW
Coal121,846 MW
Solar+Battery191,174 MW
Solar+Gas1560 MW

Counties

CountyProjectsRequested capacity
Polk21729,797 MW
Hillsborough1269,796 MW
Osceola8410,263 MW
Suwannee809,236 MW
Hendry634,870 MW
Alachua604,024 MW
Manatee547,107 MW
Citrus5312,353 MW
Duval534,562 MW
Levy5118,544 MW
Hamilton503,458 MW
Pinellas468,810 MW
Gilchrist455,197 MW
Pasco4513,530 MW
Hardee407,892 MW
Palm Beach396,689 MW
Okeechobee394,656 MW
Martin375,022 MW
Escambia373,915 MW
Orange362,996 MW
Highlands362,514 MW
Brevard354,451 MW
Volusia349,841 MW
Miami Dade323,263 MW
St. Lucie322,384 MW
Desoto262,164 MW
Collier251,494 MW
Columbia251,873 MW
Putnam243,331 MW
Lake234,896 MW
Charlotte221,431 MW
Madison221,630 MW
Broward225,473 MW
Calhoun212,136 MW
Indian River212,141 MW
Jackson20982 MW
St Lucie203,763 MW
Gadsden191,241 MW
Leon181,153 MW
Hernando174,400 MW

Largest projects

ProjectQueue IDTechnologyCapacityStatusLocation
Southeast Queue Project 2 — Gas in Polk, Florida2Gas1,701.0 MWoperationalPolk, Florida
Duke Energy Florida, LLC027100Gas1,701.0 MWactivePolk, Florida
Duke Energy Florida, LLC027240Gas1,400.0 MWwithdrawnPasco, Florida
Southeast Queue Project 109 — Gas in Pasco, Florida109Gas1,400.0 MWwithdrawnPasco, Florida
Southeast Queue Project 110 — Gas in Pasco, Florida110Gas1,400.0 MWwithdrawnPasco, Florida
Duke Energy Florida, LLC Clu Gs rt oe ur pSub Inte Cr uco stn on mec et rion Queue027238Gas1,400.0 MWwithdrawnPasco Florida County Facility, Florida
FL Queue Project 107 — Other in Miami-Dade, Florida107Other1,300.0 MWactiveMiami-Dade, Florida
FL Queue Project 108 — Other in Miami-Dade, Florida108Other1,300.0 MWactiveMiami-Dade, Florida
Southeast Queue Project 94 — Gas in Taylor, Florida94Gas1,268.0 MWwithdrawnTaylor, Florida
FL Queue Project 027086 — Gas in Taylor, Florida027086Gas1,268.0 MWwithdrawnTaylor, Florida
Southeast Queue Project 92 — Gas in Hernando, Florida92Gas1,263.0 MWwithdrawnHernando, Florida
FL Queue Project 027068 — Gas in Hernando, Florida027068Gas1,263.0 MWwithdrawnHernando, Florida
Southeast Queue Project 118 — Other in Levy, Florida118Other1,211.0 MWwithdrawnLevy, Florida
Duke Energy Florida, LLC027274—1,211.0 MWwithdrawnLevy, Florida
Duke Energy Florida, LLC027272—1,211.0 MWwithdrawnLevy, Florida
Southeast Queue Project 119 — Other in Levy, Florida119Other1,211.0 MWwithdrawnLevy, Florida
FL Queue Project 027088 — Gas in Taylor, Florida027088Gas1,204.0 MWwithdrawnTaylor, Florida
Southeast Queue Project 95 — Gas in Taylor, Florida95Gas1,204.0 MWwithdrawnTaylor, Florida
Southeast Queue Project 16 — Gas in an unlisted county, Florida16Gas1,190.0 MWwithdrawnFlorida
FL Queue Project 16 — Gas in an unlisted county, Florida16Gas1,190.0 MWwithdrawnFlorida
FL Queue Project 243 — Gas in Broward, Florida243Gas1,182.0 MWoperationalBroward, Florida
Southeast Queue Project 143 — Gas in Volusia, Florida143Gas1,180.0 MWwithdrawnVolusia, Florida
FL Queue Project 027074 — Gas in Volusia, Florida027074Gas1,180.0 MWwithdrawnVolusia, Florida
Southeast Queue Project 157 — Gas in Volusia, Florida157Gas1,174.0 MWwithdrawnVolusia, Florida
FL Queue Project 027058 — Gas in Volusia, Florida027058Gas1,174.0 MWwithdrawnVolusia, Florida
Southeast Queue Project 8 — Nuclear in Sumter, Florida8Nuclear1,150.0 MWwithdrawnSumter, Florida
Duke Energy Florida, LLC027204Other1,150.0 MWwithdrawnLevy, Florida
Southeast Queue Project 104 — Nuclear in Levy, Florida104Nuclear1,150.0 MWwithdrawnLevy, Florida
Southeast Queue Project 46 — Nuclear in Levy, Florida46Nuclear1,150.0 MWwithdrawnLevy, Florida
Duke Energy Florida, LLC027188Other1,150.0 MWwithdrawnLevy, Florida

Top developers in Florida

Recent material changes

ObservedProjectFieldOldNew
2026-10-02Brewster Solarcapacity_mw42.740
2026-10-02Bailey Mill Solarproposed_online_date2026-08-012026-09-01
2026-10-02Highland Solar Southproposed_online_date2026-08-012026-09-01
2026-09-02Highland Solar Southproposed_online_date2026-07-012026-08-01
2026-09-02Pace Road Battery Storagenew_project—active

Explore related data

Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: duke-def-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); fpl-oasis; jea-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; seminole-oasis; soco-oatt-queue; teco-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.