FL Queue Project 22 — Gas in an unlisted county, Florida

FL Queue Project 22 — Gas in an unlisted county, Florida is a 136.0 MW gas interconnection project with a current status of active. It is proposed to connect at MGS Switchyard.

136.0 MWCapacity
ActiveStatus
FLMarket
GasTechnology

Project facts

Canonical nameFL Queue Project 22 — Gas in an unlisted county, Florida
Queue ID22
Statusactive
Source statusStudy Complete TSR Complete
MarketFL
TechnologyGas
Capacity136.0 MW
StateFlorida
County
Point of interconnectionMGS Switchyard
Requested (queue) date2018-08-30
Proposed in-service date2019-12-15
Operational date
Withdrawn date
Developer
Utility / transmission ownerSeminole Electric Cooperative

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: seminole-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata