Flat Creek Storage (1559)

Flat Creek Storage is a 300.0 MW battery interconnection project in Montgomery, New York with a current status of withdrawn. It is proposed to connect at Edic to Princetown 345kV Line 352.

300.0 MWCapacity
WithdrawnStatus
FMarket
BatteryTechnology

Project facts

Canonical nameFlat Creek Storage
Queue ID1559
Statuswithdrawn
Source status0
MarketF
TechnologyBattery
Capacity300.0 MW
StateNew York
CountyMontgomery
Point of interconnectionEdic to Princetown 345kV Line 352
Requested (queue) date2023-05-22
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperSED NY Holdings LLC
Utility / transmission ownerNYPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.