Flemingsburg - Spurlock 138 kV (AH1-666 - formerly AF1-256 - moved to TC2)

Flemingsburg - Spurlock 138 kV is a 80.0 MW solar interconnection project in Fleming, Kentucky with a current status of active.

80.0 MWCapacity
ActiveStatus
—Market
SolarTechnology

Project facts

Canonical nameFlemingsburg - Spurlock 138 kV
Queue IDAH1-666 - formerly AF1-256 - moved to TC2
Statusactive
Source statusActive
Market—
TechnologySolar
Capacity80.0 MW
StateKentucky
CountyFleming
Point of interconnection—
Requested (queue) date2019-09-30
Proposed in-service date2027-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerEKPC

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-01proposed_online_date—2027-12-31medium
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.