Flynn Energy Storage (1402)
Flynn Energy Storage is a 160.0 MW battery interconnection project in Suffolk, New York with a current status of withdrawn. It is proposed to connect at Holtsville 138 kV substation.
160.0 MWCapacity
WithdrawnStatus
KMarket
BatteryTechnology
Project facts
| Canonical name | Flynn Energy Storage |
|---|---|
| Queue ID | 1402 |
| Status | withdrawn |
| Source status | 0 |
| Market | K |
| Technology | Battery |
| Capacity | 160.0 MW |
| State | New York |
| County | Suffolk |
| Point of interconnection | Holtsville 138 kV substation |
| Requested (queue) date | 2022-07-01 |
| Proposed in-service date | 2024-05-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | NY Power Authority |
| Utility / transmission owner | LIPA |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata