Fort Dodge 115 kV Substation (ERAS-2025-033)

Fort Dodge 115 kV Substation is a 150.0 MW solar interconnection project in Dodge City, Kansas with a current status of active. It is proposed to connect at Fort Dodge 115 kV Substation.

150.0 MWCapacity
ActiveStatus
KSMarket
SolarTechnology

Project facts

Canonical nameFort Dodge 115 kV Substation
Queue IDERAS-2025-033
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketKS
TechnologySolar
Capacity150.0 MW
StateKansas
CountyDodge City
Point of interconnectionFort Dodge 115 kV Substation
Requested (queue) date2025-10-01
Proposed in-service date2027-01-15
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerSEPC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-10proposed_online_date2027-05-012027-01-15medium
2026-10-03operational_date2027-03-15—medium
2026-10-03proposed_online_date—2027-05-01medium
2026-10-03statusoperationalactivehigh
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata