SEPC — Interconnection Queue Projects

SEPC is associated with 4 tracked interconnection projects representing 1,300 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

4Projects
0Active
4Operational
0Withdrawn
1,300 MWRequested capacity
0Markets

Capacity by technology

TechnologyProjectsRequested capacity
Solar3700 MW
Gas1600 MW

Geographic footprint

StateProjects
Kansas4

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Holcomb 345 kV SubstationERAS-2025-017Gas600.0 MWoperationalGarden City, Kansas
Holcomb 345 kV SubstationERAS-2025-015Solar400.0 MWoperationalGarden City, Kansas
Fort Dodge 115 kV SubstationERAS-2025-033Solar150.0 MWoperationalDodge City, Kansas
St. John 115 kV SubstationERAS-2025-032Solar150.0 MWoperationalSt. John, Kansas

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Track queue activity connecting through SEPC.

Start tracking with interXdata