SEPC — Interconnection Queue Projects

SEPC is associated with 4 tracked interconnection projects representing 1,300 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

4Projects
4Active
0Operational
0Withdrawn
1,300 MWRequested capacity
0Markets

Capacity by technology

TechnologyProjectsRequested capacity
Solar3700 MW
Gas1600 MW

Geographic footprint

StateProjects
Kansas4

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Holcomb 345 kV SubstationERAS-2025-017Gas600.0 MWactiveGarden City, Kansas
Holcomb 345 kV SubstationERAS-2025-015Solar400.0 MWactiveGarden City, Kansas
Fort Dodge 115 kV SubstationERAS-2025-033Solar150.0 MWactiveDodge City, Kansas
St. John 115 kV SubstationERAS-2025-032Solar150.0 MWactiveSt. John, Kansas

Recent material changes

ObservedProjectFieldOldNew
2026-11-10Fort Dodge 115 kV Substationproposed_online_date2027-05-012027-01-15
2026-10-03Holcomb 345 kV Substationstatusoperationalactive
2026-10-03Holcomb 345 kV Substationproposed_online_date—2029-12-14
2026-10-03Holcomb 345 kV Substationoperational_date2029-05-17—
2026-10-03Holcomb 345 kV Substationstatusoperationalactive
2026-10-03Holcomb 345 kV Substationproposed_online_date—2029-12-14
2026-10-03Holcomb 345 kV Substationoperational_date2029-05-15—
2026-10-03St. John 115 kV Substationoperational_date2025-03-02—
2026-10-03St. John 115 kV Substationproposed_online_date—2029-10-02
2026-10-03St. John 115 kV Substationstatusoperationalactive
2026-10-03Fort Dodge 115 kV Substationoperational_date2027-03-15—
2026-10-03Fort Dodge 115 kV Substationproposed_online_date—2027-05-01

Explore related data

Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.