Frackville-Siegfried 230 kV (AE1-058)

Frackville-Siegfried 230 kV is a 500.0 MW other interconnection project in Schuylkill, Pennsylvania with a current status of withdrawn.

500.0 MWCapacity
WithdrawnStatus
Market
OtherTechnology

Project facts

Canonical nameFrackville-Siegfried 230 kV
Queue IDAE1-058
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyOther
Capacity500.0 MW
StatePennsylvania
CountySchuylkill
Point of interconnection
Requested (queue) date2018-07-26
Proposed in-service date2022-12-15
Operational date
Withdrawn date2023-10-13
Developer
Utility / transmission ownerPPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata