Galion 115 kV Substation (J2956)

Galion 115 kV Substation is a 100.0 MW solar interconnection project in Morehouse, Louisiana with a current status of withdrawn. It is proposed to connect at Galion 115 kV Substation.

100.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameGalion 115 kV Substation
Queue IDJ2956
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity100.0 MW
StateLouisiana
CountyMorehouse
Point of interconnectionGalion 115 kV Substation
Requested (queue) date2022-09-15
Proposed in-service date2027-03-01
Operational date2027-03-01
Withdrawn date2026-10-20
Developer—
Utility / transmission ownerMISO

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-05withdrawn_date—2026-10-20high
2026-11-05statusoperationalwithdrawnhigh
2026-10-31phasePhase 2Phase 3low
2026-10-14phasePhase 1Phase 2low
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.