Garden City (1336_S3)

Garden City is a 16.0 MW gas interconnection project in Finney, Kansas with a current status of operational.

16.0 MWCapacity
OperationalStatus
SWPPMarket
GasTechnology

Project facts

Canonical nameGarden City
Queue ID1336_S3
Statusoperational
Source status(SB) Standby/Backup: available for service but not normally used
MarketSWPP
TechnologyGas
Capacity16.0 MW
StateKansas
CountyFinney
Point of interconnection
Requested (queue) date
Proposed in-service date
Operational date1968-06-01
Withdrawn date
Developer
Utility / transmission ownerSunflower Electric Power Corp

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectoperationalhigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata