Gardner Draw Solar (27INR0355)

Gardner Draw Solar is a 309.5 MW solar interconnection project in Glasscock, Texas with a current status of operational. It is proposed to connect at 59902 Sand Bluff 345kV .

309.5 MWCapacity
OperationalStatus
GlasscockMarket
SolarTechnology

Project facts

Canonical nameGardner Draw Solar
Queue ID27INR0355
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketGlasscock
TechnologySolar
Capacity309.5 MW
StateTexas
CountyGlasscock
Point of interconnection59902 Sand Bluff 345kV
Requested (queue) date2024-10-01
Proposed in-service date
Operational date2027-12-31
Withdrawn date
DeveloperRWE Solar Development, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata