Gas Turbine (1393)

Gas Turbine is a 233.0 MW gas interconnection project in Fairfield, Connecticut with a current status of withdrawn. It is proposed to connect at Eversource Middleriver substation 115kv.

233.0 MWCapacity
WithdrawnStatus
SWCTMarket
GasTechnology

Project facts

Canonical nameGas Turbine
Queue ID1393
Statuswithdrawn
Source statusW
MarketSWCT
TechnologyGas
Capacity233.0 MW
StateConnecticut
CountyFairfield
Point of interconnectionEversource Middleriver substation 115kv
Requested (queue) date2023-05-03
Proposed in-service date2026-06-01
Operational date
Withdrawn date2023-09-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata