Gas Turbine (155)

Gas Turbine is a 160.0 MW gas interconnection project in Middlesex, Massachusetts with a current status of withdrawn. It is proposed to connect at NSTAR Mystic Substation.

160.0 MWCapacity
WithdrawnStatus
BOSTMarket
GasTechnology

Project facts

Canonical nameGas Turbine
Queue ID155
Statuswithdrawn
Source statusW
MarketBOST
TechnologyGas
Capacity160.0 MW
StateMassachusetts
CountyMiddlesex
Point of interconnectionNSTAR Mystic Substation
Requested (queue) date2006-06-02
Proposed in-service date2011-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerISO-NE

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.