Gas Turbine is a 40.0 MW gas interconnection project in Hartford, Connecticut with a current status of withdrawn. It is proposed to connect at CL&P Windsor locks substation.

40.0 MWCapacity
WithdrawnStatus
CTMarket
GasTechnology

Project facts

Canonical nameGas Turbine
Queue ID204
Statuswithdrawn
Source statusW
MarketCT
TechnologyGas
Capacity40.0 MW
StateConnecticut
CountyHartford
Point of interconnectionCL&P Windsor locks substation
Requested (queue) date2007-03-30
Proposed in-service date2009-12-31
Operational date
Withdrawn date2007-04-27
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata