Gatsby Energy Storage (27INR0139)

Gatsby Energy Storage is a 103.4 MW other interconnection project in Pecos, Texas with a current status of operational. It is proposed to connect at Fort Lancaster 138 kV Substation (PSSE Bus #76579).

103.4 MWCapacity
OperationalStatus
PecosMarket
OtherTechnology

Project facts

Canonical nameGatsby Energy Storage
Queue ID27INR0139
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketPecos
TechnologyOther
Capacity103.4 MW
StateTexas
CountyPecos
Point of interconnectionFort Lancaster 138 kV Substation (PSSE Bus #76579)
Requested (queue) date2024-02-07
Proposed in-service date—
Operational date2030-12-31
Withdrawn date—
DeveloperGatsby Energy Storage LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-30operational_date2027-03-312030-12-31medium
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-30
Data last materially changed2026-10-30
Page data generated2026-11-26

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata