GEN-2008-053 (GEN-2008-053)

GEN-2008-053 is a 150.0 MW wind interconnection project in Gray County, Texas with a current status of withdrawn.

150.0 MWCapacity
WithdrawnStatus
TXMarket
WindTechnology

Project facts

Canonical nameGEN-2008-053
Queue IDGEN-2008-053
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyWind
Capacity150.0 MW
StateTexas
CountyGray County
Point of interconnection
Requested (queue) date2008-06-02
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata