Generator Increase (802)
Generator Increase is a 2.1 MW other interconnection project in Hartford, Connecticut with a current status of withdrawn. It is proposed to connect at Connecticut Light and Powers 13.8 kv Forestville 12A Substation.
2.1 MWCapacity
WithdrawnStatus
CTMarket
OtherTechnology
Project facts
| Canonical name | Generator Increase |
|---|---|
| Queue ID | 802 |
| Status | withdrawn |
| Source status | W |
| Market | CT |
| Technology | Other |
| Capacity | 2.1 MW |
| State | Connecticut |
| County | Hartford |
| Point of interconnection | Connecticut Light and Powers 13.8 kv Forestville 12A Substation |
| Requested (queue) date | 2018-12-04 |
| Proposed in-service date | 2019-09-03 |
| Operational date | — |
| Withdrawn date | 2019-08-06 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.