Georgia Power 24-SIC-004 is a 183.0 MW solar interconnection project in Baldwin County, Georgia with a current status of active. It is proposed to connect at Gordon - Milledgeville (White) 115 kV Line.

183.0 MWCapacity
ActiveStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power 24-SIC-004
Queue ID24-SIC-004
Statusactive
Source statusSystem Impact Study
MarketGA
TechnologySolar
Capacity183.0 MW
StateGeorgia
CountyBaldwin County
Point of interconnectionGordon - Milledgeville (White) 115 kV Line
Requested (queue) date2024-08-30
Proposed in-service date2028-05-15
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata