interXdata tracks 1,624 interconnection projects in Georgia representing 315,137 MW of requested capacity. The dominant technology by capacity is Gas. The most active counties are Mitchell County, Fulton, Effingham County.
1,624Total projects
334Active
1,036Operational
245Withdrawn
315,137 MWRequested capacity
109,290 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 400 | 171,121 MW |
| Solar | 820 | 93,975 MW |
| Battery | 130 | 25,738 MW |
| Other | 242 | 18,776 MW |
| Solar+Battery | 30 | 5,410 MW |
| Wind | 1 | 112 MW |
| Hydro | 1 | 4 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Mitchell County | 51 | 12,756 MW |
| Fulton | 45 | 59 MW |
| Effingham County | 36 | 22,085 MW |
| Decatur County | 34 | 6,131 MW |
| Burke County | 29 | 14,281 MW |
| Heard | 28 | 8,094 MW |
| Effingham | 27 | 4,940 MW |
| Glynn County | 23 | 8,305 MW |
| Taylor County | 23 | 2,704 MW |
| Jefferson County | 23 | 3,806 MW |
| Lowndes | 21 | 196 MW |
| Hancock County | 21 | 16,281 MW |
| Bartow County | 21 | 8,683 MW |
| Washington County | 20 | 5,301 MW |
| Chatham | 19 | 249 MW |
| Cobb | 19 | 2,869 MW |
| Washington | 19 | 2,330 MW |
| Floyd County | 18 | 4,886 MW |
| Burke | 17 | 5,242 MW |
| Walton | 17 | 1,921 MW |
| Putnam County | 17 | 7,257 MW |
| Macon County | 16 | 1,756 MW |
| Sumter County | 16 | 3,672 MW |
| Heard County | 16 | 12,222 MW |
| Turner County | 16 | 2,619 MW |
| Laurens County | 15 | 2,816 MW |
| Early County | 15 | 5,581 MW |
| Dodge County | 15 | 2,160 MW |
| Murray | 14 | 1,802 MW |
| Richmond | 14 | 128 MW |
| Glynn | 14 | 650 MW |
| Coweta County | 14 | 6,834 MW |
| Mitchell | 13 | 1,712 MW |
| Taylor | 13 | 414 MW |
| Camden | 13 | 60 MW |
| Bartow | 13 | 6,726 MW |
| Coffee County | 12 | 2,217 MW |
| McDuffie County | 11 | 2,717 MW |
| Jeff Davis | 11 | 820 MW |
| Jackson County | 11 | 4,926 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Georgia Power IC-244 | IC-244 | Gas | 4,375.0 MW | withdrawn | Hancock County, Georgia |
| Georgia Power IC-243 | IC-243 | Gas | 4,375.0 MW | withdrawn | Hancock County, Georgia |
| Georgia Power IC-958 | IC-958 | Gas | 2,131.0 MW | withdrawn | Cobb County, Georgia |
| Georgia Power IC-231 | IC-231 | Gas | 2,100.9 MW | withdrawn | Cobb County, Georgia |
| Smarr CC | GI-193 | Gas | 2,000.0 MW | active | Monroe County, Georgia |
| Plant Branch (2) CCs | IC-242 | Gas | 1,922.0 MW | operational | Putnam County, Georgia |
| Georgia Power 26-IC-1482 | 26-IC-1482 | Gas | 1,500.0 MW | active | Mitchell County, Georgia |
| Georgia Power IC-066 | IC-066 | Gas | 1,240.0 MW | withdrawn | Effingham County, Georgia |
| Georgia Power IC-010 | IC-010 | Gas | 1,240.0 MW | withdrawn | Murray County, Georgia |
| Georgia Power IC-128 | IC-128 | Gas | 1,240.0 MW | withdrawn | Effingham County, Georgia |
| Georgia Power IC-057 | IC-057 | Gas | 1,220.0 MW | withdrawn | Heard County, Georgia |
| Georgia Power 25-IC-1300 | 25-IC-1300 | Gas | 1,217.0 MW | active | Burke County, Georgia |
| Vogtle | 649_1 | Other | 1,215.0 MW | operational | Burke, Georgia |
| Vogtle | 649_2 | Other | 1,215.0 MW | operational | Burke, Georgia |
| Georgia Power 25-IC-1298 | 25-IC-1298 | Gas | 1,210.0 MW | active | Burke County, Georgia |
| Pepper Hammock Solar and Storage | 68367_PEHA1 | Solar | 1,200.0 MW | active | Wayne, Georgia |
| IC-Pepper Hammock II | IC-942 | Solar | 1,200.0 MW | operational | Glynn County, Georgia |
| Georgia Power IC-215 | IC-215 | Gas | 1,200.0 MW | withdrawn | Early County, Georgia |
| Georgia Power IC-216 | IC-216 | Gas | 1,200.0 MW | withdrawn | Early County, Georgia |
| Georgia Power IC-206 | IC-206 | Gas | 1,195.0 MW | withdrawn | Heard County, Georgia |
| Georgia Power 25-IC-1299 | 25-IC-1299 | Gas | 1,167.0 MW | active | Burke County, Georgia |
| Georgia Power 25-IC-1297 | 25-IC-1297 | Gas | 1,160.0 MW | active | Burke County, Georgia |
| Georgia Power IC-237 | IC-237 | Gas | 1,158.0 MW | withdrawn | Burke County, Georgia |
| Georgia Power IC-236 | IC-236 | Gas | 1,158.0 MW | operational | Burke County, Georgia |
| Georgia Power 25-IC-1305 | 25-IC-1305 | Gas | 1,151.0 MW | withdrawn | Burke County, Georgia |
| Georgia Power 25-IC-1303 | 25-IC-1303 | Gas | 1,141.0 MW | active | Burke County, Georgia |
| Georgia Power 25-IC-1304 | 25-IC-1304 | Gas | 1,137.0 MW | active | Burke County, Georgia |
| Vogtle | 649_3 | Other | 1,114.0 MW | operational | Burke, Georgia |
| Vogtle | 649_4 | Other | 1,114.0 MW | operational | Burke, Georgia |
| Georgia Power IC-044 | IC-044 | Gas | 1,100.0 MW | withdrawn | Effingham County, Georgia |
Top developers in Georgia
Developer attribution is not yet resolved for this set.
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-10-02 | Yates | proposed_online_date | 2026-12-01 | 2027-02-01 |
| 2026-10-02 | McGrau Ford Battery Storage Facility | operational_date | — | 2026-08-01 |
| 2026-10-02 | McGrau Ford Battery Storage Facility | proposed_online_date | 2026-08-01 | — |
| 2026-10-02 | McGrau Ford Battery Storage Facility | status | active | operational |
| 2026-10-02 | McGrau Ford Battery Storage Facility | operational_date | — | 2026-08-01 |
| 2026-10-02 | McGrau Ford Battery Storage Facility | proposed_online_date | 2026-08-01 | — |
| 2026-10-02 | McGrau Ford Battery Storage Facility | status | active | operational |
| 2026-09-02 | Prologis Portside 2509 - SLSAV502 | operational_date | — | 2026-06-01 |
| 2026-09-02 | Prologis Portside 2509 - SLSAV502 | proposed_online_date | 2026-06-01 | — |
| 2026-09-02 | Prologis Portside 2509 - SLSAV502 | status | active | operational |
| 2026-09-02 | Pepper Hammock Solar and Storage | proposed_online_date | 2028-12-01 | 2029-09-01 |
| 2026-09-02 | Pepper Hammock Solar and Storage | proposed_online_date | 2027-08-01 | 2029-09-01 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); gtc-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get notified when a new project appears in Georgia.
Start tracking with interXdata