Georgia Power 24C-IC-1232 (24C-IC-1232)
Georgia Power 24C-IC-1232 is a 200.0 MW solar interconnection project in Lee County, Georgia with a current status of withdrawn. It is proposed to connect at North Americus - Palmyra 230 kV Line.
200.0 MWCapacity
WithdrawnStatus
GAMarket
SolarTechnology
Project facts
| Canonical name | Georgia Power 24C-IC-1232 |
|---|---|
| Queue ID | 24C-IC-1232 |
| Status | withdrawn |
| Source status | Request Withdrawn |
| Market | GA |
| Technology | Solar |
| Capacity | 200.0 MW |
| State | Georgia |
| County | Lee County |
| Point of interconnection | North Americus - Palmyra 230 kV Line |
| Requested (queue) date | 2024-01-08 |
| Proposed in-service date | 2027-06-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Georgia Power |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.