Georgia Power 24C-IC-1272 (24C-IC-1272)

Georgia Power 24C-IC-1272 is a 200.0 MW battery interconnection project in Paulding County, Georgia with a current status of active. It is proposed to connect at McConnell - Pegamore 230 kV Line.

200.0 MWCapacity
ActiveStatus
GAMarket
BatteryTechnology

Project facts

Canonical nameGeorgia Power 24C-IC-1272
Queue ID24C-IC-1272
Statusactive
Source statusGIA in Suspension
MarketGA
TechnologyBattery
Capacity200.0 MW
StateGeorgia
CountyPaulding County
Point of interconnectionMcConnell - Pegamore 230 kV Line
Requested (queue) date2024-03-27
Proposed in-service date2030-04-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.