Georgia Power 25-IC-1327 (25-IC-1327)

Georgia Power 25-IC-1327 is a 759.1 MW gas interconnection project in Coweta County, Georgia with a current status of active. It is proposed to connect at Dyer Road Substation 230 kV Bus.

759.1 MWCapacity
ActiveStatus
GAMarket
GasTechnology

Project facts

Canonical nameGeorgia Power 25-IC-1327
Queue ID25-IC-1327
Statusactive
Source statusGIA Draft
MarketGA
TechnologyGas
Capacity759.1 MW
StateGeorgia
CountyCoweta County
Point of interconnectionDyer Road Substation 230 kV Bus
Requested (queue) date2025-04-11
Proposed in-service date2030-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.