Georgia Power 26-SIC-017 (26-SIC-017)

Georgia Power 26-SIC-017 is a 225.0 MW solar interconnection project in Laurens County, Georgia with a current status of active. It is proposed to connect at North Dublin - Wadley Primary 230 kV Line.

225.0 MWCapacity
ActiveStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power 26-SIC-017
Queue ID26-SIC-017
Statusactive
Source statusSystem Impact Study
MarketGA
TechnologySolar
Capacity225.0 MW
StateGeorgia
CountyLaurens County
Point of interconnectionNorth Dublin - Wadley Primary 230 kV Line
Requested (queue) date2026-02-10
Proposed in-service date2028-07-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.