Georgia Power IC-1228 (IC-1228)

Georgia Power IC-1228 is a 225.0 MW solar interconnection project in Taylor County, Georgia with a current status of withdrawn. It is proposed to connect at Butler DS Substation 230 kV Bus.

225.0 MWCapacity
WithdrawnStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power IC-1228
Queue IDIC-1228
Statuswithdrawn
Source statusRequest Withdrawn
MarketGA
TechnologySolar
Capacity225.0 MW
StateGeorgia
CountyTaylor County
Point of interconnectionButler DS Substation 230 kV Bus
Requested (queue) date2024-01-08
Proposed in-service date2027-06-03
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.