Georgia Power IC-229 (IC-229)

Georgia Power IC-229 is a 53.0 MW gas interconnection project in Lamar County, Georgia with a current status of operational. It is proposed to connect at Barnesville Primary - Rumble Rd 115 kV line.

53.0 MWCapacity
OperationalStatus
GAMarket
GasTechnology

Project facts

Canonical nameGeorgia Power IC-229
Queue IDIC-229
Statusoperational
Source statusCommercial Operation
MarketGA
TechnologyGas
Capacity53.0 MW
StateGeorgia
CountyLamar County
Point of interconnectionBarnesville Primary - Rumble Rd 115 kV line
Requested (queue) date2009-05-01
Proposed in-service date2011-11-01
Operational date2011-11-01
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata