Georgia Power IC-230 (IC-230)
Georgia Power IC-230 is a 487.2 MW gas interconnection project in Cobb County, Georgia with a current status of operational. It is proposed to connect at Atkinson Substation 115 kV Bus.
487.2 MWCapacity
OperationalStatus
GAMarket
GasTechnology
Project facts
| Canonical name | Georgia Power IC-230 |
|---|---|
| Queue ID | IC-230 |
| Status | operational |
| Source status | Commercial Operation |
| Market | GA |
| Technology | Gas |
| Capacity | 487.2 MW |
| State | Georgia |
| County | Cobb County |
| Point of interconnection | Atkinson Substation 115 kV Bus |
| Requested (queue) date | 2009-07-30 |
| Proposed in-service date | 2010-02-15 |
| Operational date | 2010-02-15 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Georgia Power |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata