Georgia Power IC-343 (IC-343)

Georgia Power IC-343 is a 100.0 MW solar interconnection project in Taylor County, Georgia with a current status of operational. It is proposed to connect at Butler DS Substation 230 kV Bus.

100.0 MWCapacity
OperationalStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power IC-343
Queue IDIC-343
Statusoperational
Source statusCommercial Operation
MarketGA
TechnologySolar
Capacity100.0 MW
StateGeorgia
CountyTaylor County
Point of interconnectionButler DS Substation 230 kV Bus
Requested (queue) date2014-03-12
Proposed in-service date2016-05-31
Operational date2016-05-31
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata