Georgia Power IC-592 (IC-592)

Georgia Power IC-592 is a 663.6 MW gas interconnection project in Whitfield County, Georgia with a current status of operational. It is proposed to connect at Conasauga Substation.

663.6 MWCapacity
OperationalStatus
GAMarket
GasTechnology

Project facts

Canonical nameGeorgia Power IC-592
Queue IDIC-592
Statusoperational
Source statusCommercial Operation
MarketGA
TechnologyGas
Capacity663.6 MW
StateGeorgia
CountyWhitfield County
Point of interconnectionConasauga Substation
Requested (queue) date2017-02-01
Proposed in-service date2018-04-23
Operational date2018-04-23
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata