Georgia Power IC-694 (IC-694)
Georgia Power IC-694 is a 615.0 MW solar interconnection project in Sumter County, Georgia with a current status of active. It is proposed to connect at Fortson - North Tifton 500 kV Line.
615.0 MWCapacity
ActiveStatus
GAMarket
SolarTechnology
Project facts
| Canonical name | Georgia Power IC-694 |
|---|---|
| Queue ID | IC-694 |
| Status | active |
| Source status | GIA with NTP |
| Market | GA |
| Technology | Solar |
| Capacity | 615.0 MW |
| State | Georgia |
| County | Sumter County |
| Point of interconnection | Fortson - North Tifton 500 kV Line |
| Requested (queue) date | 2018-05-03 |
| Proposed in-service date | 2023-04-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Georgia Power |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | active | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata