Georgia Power IC-769 (IC-769)

Georgia Power IC-769 is a 140.0 MW solar interconnection project in Oglethorpe County, Georgia with a current status of operational. It is proposed to connect at East Watkinsville - Russell Dam (USA) 230 kV Line.

140.0 MWCapacity
OperationalStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power IC-769
Queue IDIC-769
Statusoperational
Source statusCommercial Operation
MarketGA
TechnologySolar
Capacity140.0 MW
StateGeorgia
CountyOglethorpe County
Point of interconnectionEast Watkinsville - Russell Dam (USA) 230 kV Line
Requested (queue) date2018-12-21
Proposed in-service date2023-06-01
Operational date2023-06-01
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata