Georgia Power IC-805 (IC-805)

Georgia Power IC-805 is a 195.5 MW solar interconnection project in Mitchell County, Georgia with a current status of operational. It is proposed to connect at Scooter Substation 230 kV Bus.

195.5 MWCapacity
OperationalStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power IC-805
Queue IDIC-805
Statusoperational
Source statusCommercial Operation
MarketGA
TechnologySolar
Capacity195.5 MW
StateGeorgia
CountyMitchell County
Point of interconnectionScooter Substation 230 kV Bus
Requested (queue) date2019-09-23
Proposed in-service date2021-08-15
Operational date2021-08-15
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.