Georgia Power IC-878 (IC-878)

Georgia Power IC-878 is a 135.0 MW solar interconnection project in Mitchell County, Georgia with a current status of withdrawn. It is proposed to connect at Scooter Substation 230 kV Bus.

135.0 MWCapacity
WithdrawnStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power IC-878
Queue IDIC-878
Statuswithdrawn
Source statusGIA Terminated
MarketGA
TechnologySolar
Capacity135.0 MW
StateGeorgia
CountyMitchell County
Point of interconnectionScooter Substation 230 kV Bus
Requested (queue) date2020-06-03
Proposed in-service date2023-01-17
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata