Georgia Power IC-909 (IC-909)

Georgia Power IC-909 is a 220.0 MW solar interconnection project in Turner County, Georgia with a current status of withdrawn. It is proposed to connect at North Tifton - Pitts 230 kV Line.

220.0 MWCapacity
WithdrawnStatus
GAMarket
SolarTechnology

Project facts

Canonical nameGeorgia Power IC-909
Queue IDIC-909
Statuswithdrawn
Source statusGIA Terminated
MarketGA
TechnologySolar
Capacity220.0 MW
StateGeorgia
CountyTurner County
Point of interconnectionNorth Tifton - Pitts 230 kV Line
Requested (queue) date2020-10-09
Proposed in-service date2023-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.